Lot 22 - The Maple

Delayed

456 Sunset Ridge Dr

Sunset Ridge Phase 2

Construction Timeline

Pre-Construction
Foundation
3
Framing
75%
4
MEP Rough-In
5
Insulation & Drywall
6
Interior Finishes
7
Exterior Finishes
8
Final Punch List

Progress Overview

Stages Completed2 of 8
Current Stage:Framing
Est. Completion:2024-12-20

Current Action Items

4 items
Structural Engineering Review
ApprovalFraming
Structural modifications required - see comments
Rejected
✍️
1 Pending Approval
Requires attention
📝
2 Change Orders
In progress

Historical Artifacts

5 items

Foundation

📸
Foundation Pour Complete
Photo Update8/19/2024Mike Johnson (Site Supervisor)
Foundation concrete pour completed successfully. Curing process has begun.
📸 3 photos
Update
🏆
Foundation Pour Certificate
Certificate8/19/2024
Concrete pour completion certificate
Approved
⚠️
Weather Delay - Foundation Pour
Issue Report8/15/2024Sarah Wilson (Project Manager)
Heavy rain forecast for next 3 days. Postponing foundation pour to ensure proper curing conditions.
Update

Pre-Construction

🎯
Site Preparation Complete
Milestone7/28/2024Carlos Martinez (Site Foreman)
Site clearing and grading completed. Foundation excavation ready to begin.
Update
🏆
Site Survey Report
Certificate7/10/2024
Completed site survey and soil analysis
Final

Project Details

Lot Number
22
Square Feet
2,100
Bedrooms
3
Bathrooms
2.5
Price
$425,000
Start Date
2024-07-15

Buyer Information

S
Santos Family

Assigned Contractors

Texas Framing Solutions
Framing
David Martinez
(512) 555-0105
Lone Star Roofing
Roofing
James Wilson
(512) 555-0106