Lot 14 - The Oakwood

Active

123 Sunset Ridge Dr

Sunset Ridge Phase 2

Construction Timeline

Pre-Construction
Foundation
Framing
4
MEP Rough-In
60%
5
Insulation & Drywall
6
Interior Finishes
7
Exterior Finishes
8
Final Punch List

Progress Overview

Stages Completed3 of 8
Current Stage:MEP Rough-In
Est. Completion:2026-02-20

Current Action Items

5 items
📐
Electrical Rough-In Plans
PlanMEP Rough-In
Updated electrical plans for review
Pending Review
📝
Plumbing Change Order #1
Change OrderMEP Rough-In
Additional bathroom fixture installation
Signature Required
✍️
2 Pending Approvals
Requires attention
🔍
1 Upcoming Inspection
Scheduled

Historical Artifacts

6 items

MEP Rough-In

⚠️
Electrical Plan Revision Needed
Issue Report10/10/2024Tom Rodriguez (Electrical Contractor)
Discovered conflict with HVAC ducting placement. Need to revise electrical rough-in plans before proceeding.
Update

Framing

📈
Framing 75% Complete
Progress Update9/28/2024Sarah Wilson (Project Manager)
Framing work is progressing well. All exterior walls are up, working on interior walls and roof structure.
📸 2 photos
Update
📸
Framing Photos - Week 1
Photo9/13/2024
Progress photos from first week of framing
Final

Foundation

🎯
Foundation Inspection Passed
Milestone9/5/2024Mike Johnson (Site Supervisor)
Foundation inspection completed successfully with no issues found. Ready to proceed with framing.
Update
🔍
Foundation Inspection Report
Inspection Report9/5/2024
Passed foundation inspection
Approved

Pre-Construction

📋
Building Permit Application
Permit7/28/2024
Approved building permit for construction
Final

Project Details

Lot Number
14
Square Feet
2,450
Bedrooms
4
Bathrooms
3
Price
$485,000
Start Date
2024-08-01

Buyer Information

W
Wilson Family

Assigned Contractors

Premier Electric Co.
Electrical
Mike Johnson
(512) 555-0101
HVAC Masters
HVAC
Sarah Chen
(512) 555-0103
Quality Plumbing Inc.
Plumbing
Tom Williams
(512) 555-0104